Examveda

Which of the following reflect correct sequence of PP and C i.e. Production Planning and Control?
1. Sequencing
2. Scheduling
3. Loading
4. Monitoring

A. 1, 3, 4, 2

B. 2, 3, 4, 1

C. 2, 1, 4, 3

D. 1, 2, 3, 4

Answer: Option C