Examveda
Examveda

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take $$\frac{8}{3}$$ more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

A. 2 days

B. 4 days

C. 6 days

D. 8 days

E. 10 days

Answer: Option B

Solution(By Examveda Team)

Ratio of efficiencies of A, B and C,
= 5x : 4x : 6x
Number of days required by A and B = $$\frac{{100}}{{9{\text{x}}}}$$ ------ (1)
Number of days required by A, B and C = $$\frac{{100}}{{15{\text{x}}}}$$ ------ (2)
$$\eqalign{ & \frac{{100}}{{9{\text{x}}}} - \frac{{100}}{{15{\text{x}}}} = \frac{8}{3} \cr & \Rightarrow {\text{x}} = \frac{5}{3} \cr} $$
Number of days required by A, B and C
= $$\frac{{100}}{{15{\text{x}}}}$$
= $$\frac{{100}}{{15 \times \frac{5}{3}}}$$
= 4 days

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 6 )

  1. Rice Rice
    Rice Rice :
    4 years ago

    If a, b, and c take x days
    then b and c take 50% more days
    means x + x/2 = 3x/2 days
    ratio will be
    a+b+c : b+c = x : 3x/2 = 2x : 3x
    So ratio off efficiency becomes 3x : 2x
    Now, efficiency of A is,
    (A + B + C) - (B + C) = 3x - 2x
    A = x
    So, the efficiency of A is 1/3rd of (A+B+C) [i.e. 1/3 * 3x = x]
    Now, share of B given 120 out of 450 = 120/450 = 4/15
    We can find ratio of efficiencies now,
    A = 1/3 = 5/15
    B = 4/15
    C = (15-4-5)/15 = 6/15
    i.e. 5 : 4 : 6
    Now, ratio of number of days = 1/5 : 1/4 : 1/6
    => 60x/5 : 60x/4 : 60x/6
    => 12x : 15x : 10x

    Now, One day work of A & B = 1/12x + 1/15x = 9/60x
    So, A & B will take 60x/9 days to complete the work.
    therefore, A,B & C = 1/12x + 1/15x + 1/10x = 15/60x
    So, A,B & C will take 60x/15 days to complete the work.

    Now given that A and B take 8/3 days more than A, B and C
    So, 60x/9 - 60x/15 = 8/3
    Solving this we get x = 1
    Thus number of days A, B and C will take to complete the whole work is 60x/15 = 4x = 4*1 = 4days.

  2. Md Mahabubor
    Md Mahabubor :
    5 years ago

    12/18=2/3
    1-2/3=1/3
    Then whole work completed by B is = 3*15=45
    A's part= 1/18-1/45=1/30
    A:B= 30:45=2:3
    then A's share= 1500*2/5=600

  3. Muniruzzaman Munir
    Muniruzzaman Munir :
    5 years ago

    Let say A , B & C takes A , B & C days respectively to complete the work
    => A , B & C 's 1 day work  = 1/A , 1/B & 1/C respectively

    B& C complete work in  1/(1/B + 1/C)

    A B & C complete work in 1/(1/A + 1/B + 1/C)
    1/(1/B + 1/C)  = 1/(1/A + 1/B + 1/C)   * (3/2)
    => 2(1/A + 1/B + 1/C)  = 3(1/B + 1/C)
    => 2/A = 1/B + 1/C

    1/A + 1/B + 1/C = 1/A + 2/A = 3/A
    Time taken to complete work together by A , B & C = A/3
    work done by B in A/3 days  =  A/3B
    => A/3B  = 120/450
    => 5A = 4B
    1/(1/A + 1/B)  = A/3  + 8/3
    => 1/(1/A + 4/5A)  + A/3 + 8/3
    => 5A/9 = A/3 + 8/3
    => 5A = 3A + 24
    => 2A = 24
    => A = 12

  4. Sangeeta Rani
    Sangeeta Rani :
    6 years ago

    answear is 4 days then how is 8 days

  5. Saket
    Saket :
    9 years ago

    how was the ratio calculated here?

  6. Ashutosh Sharma
    Ashutosh Sharma :
    9 years ago

    How we find the ratio of efficiency, please reply.

Related Questions on Time and Work