Works costing less than Rs. 20,000 are treated as
A. Any project
B. Major projects
C. Minor projects
D. Petty works
Answer: Option D
A. Any project
B. Major projects
C. Minor projects
D. Petty works
Answer: Option D
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$
construction works costing below 20000/- are minor works, costing between 20000/- to 1 lac are major works, costing above 1 lac are project and costing less than 2500/- are petty works. Pls do correct the answer
plz correct thsi MCQs. The works costing less than 20,000 will be treated as ''petty works''. Moreover if the cost of the work if between 20,000 to 1,00,000 will be treated a Minor Works and the work costing more than 1,00,000 will be considered as Major Projects.
Below 20,000 is petty work
Works costing less than Rs. 20,000 are treated as Minor works.. not minor projects.
Only Works costing more than 1L is treated as project.
Below 1L are treated as works not project