X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
A. $$13\frac{1}{3}$$ days
B. 15 days
C. 20 days
D. 26 days
Answer: Option A
Solution (By Examveda Team)
Work done by X in 8 days = $$ {\frac{1}{{40}} \times 8} $$ = $$\frac{1}{5}$$Remaining work = $$ {1 - \frac{1}{5}} $$ = $$\frac{4}{5}$$
Now, $$\frac{4}{5}$$ work is done by Y in 16 days
Whole work will be done by Y in = $$ {16 \times \frac{5}{4}} $$ = 20 days
∴ X's 1 day's work = $$\frac{1}{{40}}$$
∴ Y's 1 day's work = $$\frac{1}{{20}}$$
(X + Y)'s 1 day's work
$$\eqalign{ & = {\frac{1}{{40}} + \frac{1}{{20}}} \cr & = \frac{3}{{40}} \cr} $$
Hence, X and Y will together complete the work in
$$\eqalign{ & = {\frac{{{\text{40}}}}{{\text{3}}}} \cr & {\text{ = 13}}\frac{{\text{1}}}{{\text{3}}}\,\,{\text{days}} \cr} $$
Join The Discussion
Comments (3)
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days

how to solution
Assume total work as 100units ,
And divide 100 by 40 to get the efficience of X, then u will get 2.5 units of efficiency per day.
Then later multiply 2.5 with 8 to get total work done by X , then we get 20.
20 units is the work done done by X.
Deduct 20 from 100 to know remaining work
100 - 20 = 80.
So 80 units of work is remaining.
Divide 80 by 16 to know Y's efficiency.
80/16 = 5.
So combined efficiency of X and Y is
2.5 + 5 = 7.5
So finally..
Divide 100 by 7.5
100/7.5 =13.33
That is 13⅓ days
Can you pl provide any shortcut method for this sum for reducing time...?