X, Y and Z complete a work in 6 days. X or Y alone can do the same work in 16 days. In how many days Z alone can finish the same work ?
A. 12
B. 16
C. 24
D. 36
Answer: Option C
Solution(By Examveda Team)
(X + Y)'s 1 day's work$$\eqalign{ & = \left( {\frac{1}{{16}} + \frac{1}{{16}}} \right) \cr & = \frac{2}{{16}} \cr & = \frac{1}{8} \cr} $$
∴ Z's 1 day's work
(X + Y + Z)'s 1 day's work - (X + Y)'s 1 day's work
$$\eqalign{ & = \frac{1}{6} - \frac{1}{8} \cr & = \frac{1}{{24}} \cr} $$
∴ Z alone can finish the work in 24 days.
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
Join The Discussion