After fixing the plane table to the tripod, the main operations which are needed at each plane table station are
(i) Levelling
(ii) Orientation
(iii) Centering
The correct sequence of these operations is

A. (i), (ii), (iii)

B. (i), (iii), (ii)

C. (iii), (i), (ii)

D. (ii), (iii), (i)

Answer: Option B