ExamVeda
Login
Home
31
If 2 men or 6 women or 4 boys can finish a work in 99 days, how many days will one man, one woman and one boy together take to finish the same work ?
Discuss
Answer & Solution
Answer: Option E
Solution:
$$\eqalign{ & {\text{1 men's 1 day's work}} \cr & = \frac{1}{{99 \times 2}} \cr & = \frac{1}{{198}} \cr & {\text{1 women's 1 day's work}} \cr & = \frac{1}{{99 \times 6}}. \cr & = \frac{1}{{594}} \cr & {\text{1 boy's 1 day's work}} \cr & = \frac{1}{{99 \times 4}} \cr & = \frac{1}{{396}} \cr} $$
(1 men + 1 women + boy)'s 1 day's work
$$\eqalign{ & = \frac{1}{{198}} + \frac{1}{{594}} + \frac{1}{{396}} \cr & = \frac{{11}}{{1188}} \cr & = \frac{1}{{108}} \cr} $$
Hence, 1 mens , 1 women and 1 boys together take 108 days to finish the work.
32
8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{1 men's 1 day's work}} \cr & = \frac{1}{{20 \times 8}} \cr & = \frac{1}{{160}} \cr & {\text{1 women's 1 day's work}} \cr & = \frac{1}{{32 \times 8}} \cr & = \frac{1}{{256}} \cr & \left( {{\text{5 men}} + {\text{8 women}}} \right){\text{'s 1 day's work}} \cr & = \frac{5}{{160}} + \frac{8}{{256}} \cr & = \frac{1}{{32}} + \frac{1}{{32}} \cr & = \frac{1}{{16}} \cr} $$
Hence, 5 mens and 8 women together can complete the work in 16 days.
33
A can do three times the work done by B in one day. They together finish $$\frac{2}{5}$$ of the work in 9 days. The number of days by which B can do the work alone are ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Efficiency of A = 3 efficiency of B
$$\left( {{\text{A}} = 3,{\text{B}} = 1} \right)$$
$$\frac{2}{5}$$ th of the work done by (A + B) in 9 days
Total work (A + B) = $$\frac{{45}}{2}$$ days will be completed
$$\eqalign{ & {\text{Total work}} \cr & = {\text{days}} \times {\text{efficiency }}\left( {{\text{A}} + {\text{B}}} \right) \cr & = \frac{{45}}{2} \times 4 \cr & = 90 \cr & {\text{Number of days for B }} \cr & {\text{ = }}\frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{90}}{1} \cr & = 90{\text{ days}} \cr} $$
34
A can write 75 pages in 25 hours. A and B together can write 135 pages in 27 hours. In what time can B write 42 pages ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Time and Work mcq solution image
B's efficiency
= (A + B)'s efficiency - A's efficiency
= 5 - 3
= 2 pages/hour
B's time
2 pages in 1 hour
42 pages in 21 hours
35
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be complete in ?
Discuss
Answer & Solution
Answer: Option A
Solution:
A's one day work = 3 units
B's one day work = 2 units
A starts the work and does 3 units and B does the work 2 units/day.
They both do 5 units of work in 2 days.
They both do 35 units of work in 14 days
(Divide $${\frac{{36}}{5}}$$, take it to the closest)
$$\eqalign{ & {\text{Work left }} \Rightarrow 36 - 35 = 1{\text{unit}}{\text{.}} \cr & {\text{Now, A's turn}}{\text{.}} \cr & {\text{A completes}} \cr & \Rightarrow \frac{{1{\text{ unit}}}}{{{\text{3 units/day}}}} \cr & = \frac{1}{3}{\text{ day}} \cr & {\text{Whole work completes in}} \cr & \Rightarrow 14 + \frac{1}{3} \cr & = 14\frac{1}{3}{\text{ days}} \cr} $$
36
A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?
Discuss
Answer & Solution
Answer: Option C
Solution:
If labourer had come for 20 days he would have earned = 20 × 75 = Rs. 1500
If labourer had absented for 20 days he would have earned fined for = 20 × 15 = Rs. 300
Time and Work mcq solution image
37
18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{1 men's 1 day's work}} \cr & = \frac{1}{{63 \times 18}} \cr & = \frac{1}{{1134}} \cr & {\text{1 women's 1 day's work}} \cr & = \frac{1}{{189 \times 9}} \cr & = \frac{1}{{1701}} \cr & {\text{1 children's 1 day's work}} \cr & = \frac{1}{{486 \times 7}} \cr & = \frac{1}{{3402}} \cr} $$
(4 men + 9 women + 12 children)'s 1 day's work
$$\eqalign{ & = \frac{4}{{1134}} + \frac{9}{{1701}} + \frac{{12}}{{3402}} \cr & = \frac{{42}}{{3402}} \cr & = \frac{1}{{81}} \cr} $$
Hence, 4 mens , 9 women and 12 children together will complete the work in 81 days.
38
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{1 men's 1 day's work}} \cr & = \frac{1}{{24 \times 16}} \cr & = \frac{1}{{384}} \cr & {\text{1 boy's 1 day's work}} \cr & = \frac{1}{{16 \times 48}} \cr & = \frac{1}{{768}} \cr & {\text{12 men's 4 day's work}} \cr & = \left( {\frac{{12}}{{384}} \times 4} \right) \cr & = \frac{1}{8} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{1}{8}} \right) \cr & = \frac{7}{8} \cr & \left( {{\text{12 men}} + {\text{12 boy}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{{12}}{{384}} + \frac{{12}}{{768}}} \right) \cr & = \left( {\frac{1}{{32}} + \frac{1}{{64}}} \right) \cr & = \frac{3}{{64}} \cr} $$
$$\frac{3}{{64}}$$ work is done by (12 men + 12 boy)'s in 1 day
$$\eqalign{ & \therefore \frac{7}{8}{\text{ work is done by them in }} \cr & {\text{ = }}\frac{{64}}{3} \times \frac{7}{8}{\text{ days}} \cr & = \frac{{56}}{3}{\text{ days}} \cr & = {\text{18}}\frac{2}{3}{\text{ days}} \cr} $$
39
4 men and 10 women were put on a work. They completed $$\frac{1}{3}$$ of the work in 4 days. After this 2 men and 2 women were increased. They completed $$\frac{2}{9}$$ more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & {\text{Let 1 man's 1 day's work}} = x \cr & {\text{And }} \cr & {\text{1 women's 1 day's work}} = y \cr & {\text{Then,}} \cr & \Rightarrow 4x + 10y = \frac{1}{3} \times \frac{1}{4} = \frac{1}{{12}} \cr & \Rightarrow 4x + 10y = \frac{1}{{12}} \cr & \Rightarrow 2x + 5y = \frac{1}{{24}}.....(i) \cr & {\text{And,}} \cr & \Rightarrow 6x + 12y = \frac{1}{9} \cr & \Rightarrow 2x + 4y = \frac{1}{{27}}.....({\text{ii}}) \cr} $$
Subtracting (ii) from (i), we get
$$\eqalign{ & y = \frac{1}{{24}} - \frac{1}{{27}} = \frac{1}{{216}} \cr & {\text{Now,}} \cr} $$
Now,
(6 men + 12 women)'s 3 day's work
$$\eqalign{ & = \left( {\frac{1}{9} \times 3} \right) \cr & = \frac{1}{3} \cr & {\text{Work completed}} \cr & = \left( {\frac{1}{3} + \frac{2}{9} + \frac{1}{3}} \right) \cr & = \frac{8}{9} \cr & \therefore {\text{Remainig work}} \cr & = \left( {1 - \frac{8}{9}} \right) \cr & = \frac{1}{9} \cr & {\text{1 women's 3 day's work}} \cr & = \left( {\frac{1}{{216}} \times 3} \right) \cr & = \frac{1}{{72}} \cr} $$
In 3 day's $$\frac{1}{{72}}$$ work is done by 1 women.
$$\eqalign{ & \therefore {\text{In 3 day's }}\frac{1}{9}{\text{work is done by}} \cr & {\text{ = }}\left( {72 \times \frac{1}{9}} \right) \cr & = {\text{8 women}}{\text{.}} \cr} $$
40
A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take $${\text{11}}\frac{1}{9}$$ days, then the time taken by B alone to do the same work (in days ) is ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Try these question with the help of the option to save the time
Let B takes x days to complete the work
∴ A takes (x - 5)days

Now take the option 'B' i.e x = 20days
∴ Time taken by B = 20days and A = 15days
T.W = LCM of number of day taken by A and B = 60.
Work Efficiency ration A : B = 4 : 3
∴Total Time taken to complete the work together = $$\frac{60}{4+3}$$ =   $$8\frac{4}{7}$$  days
This option not matched with $${\text{11}}\frac{1}{9}$$

Now take the option 'C' i.e x = 25days
∴ Time taken by B = 25days and A = 20days
T.W = LCM of number of day taken by A and B = 100.
Work Efficiency ration A : B = 5 : 4
∴Total Time taken to complete the work together = $$\frac{100}{5+4}$$ =   $$11\frac{1}{9}$$  days
Hence , Option (C) is the correct .