ExamVeda
Login
Home
1
30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond, in 20 days?
Discuss
Answer & Solution
Answer: Option A
Solution:
Understanding the Problem:
Imagine digging a pond. It takes a certain amount of effort. That effort is made up of the number of workers, the number of hours they work each day, and the number of days they work.

What we know:
30 men working 8 hours a day take 16 days to dig the pond.

What we want to find:
How many hours a day will 32 men need to work to dig the *same* pond in 20 days?

Think of it like this:
The total work is the same (digging the same pond). Total work is calculated as: (Number of men) x (Hours per day) x (Number of days).

Let's calculate the total work:
Total work = 30 men x 8 hours/day x 16 days = 3840 man-hours

Now, let's use the total work to find the hours needed for 32 men working for 20 days:
3840 man-hours = 32 men x (Hours per day) x 20 days

Solve for "Hours per day":
(Hours per day) = 3840 man-hours / (32 men x 20 days)
(Hours per day) = 3840 / 640 = 6 hours/day

Therefore, the answer is:
A: 6 hours/day



Alternative Solution
8 × 30 × 16 = 32 × 20 × $$x$$
$$x$$ = 6 hours per day
2
25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & 25 \times 16 = 25 \times 4 + 30 \times x \cr & \left( {{M_1} \times {D_1}} \right) = \left( {{M_1}{D_1} \times {M_2}{D_2}} \right) \cr & 400 = 100 + 30x \cr & 300 = 30x \cr & x = 10{\text{ days}} \cr} $$
3
A and B separately can build a wall in 12 and 16 days, respectively. If they work for each day alternatively, starting with A, in how many days will the wall be built?
Discuss
Answer & Solution
Answer: Option C
Solution:
Time and Work mcq question image
2 days → 4 + 3 = 7 units
12 days → 42 units
13 days → 42 + 4 = 46 units
Total time taken = $$13\frac{2}{3}{\text{ days}}$$
4
3 men and 8 women can complete a work in $$\frac{{75}}{8}$$ days. While 9 men and 12 women can complete it in $$\frac{{25}}{7}$$ days. In how many days will 15 women complete it?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & \left( {3m + 8w} \right) \times \frac{{75}}{8} = \left( {9m + 12w} \right) \times \frac{{25}}{7} \cr & 63m + 168w = 72m + 96w \cr & 72w = 9m \cr & \frac{m}{w} = \frac{8}{1} \cr & {\text{Total work}} = \left( {3m + 8w} \right) \times \frac{{75}}{8} \cr & = \left( {3 \times 8 + 8 \times 1} \right) \times \frac{{75}}{8} \cr & = 4 \times 75 \cr & {\text{Time taken by }}15w = \frac{{4 \times 75}}{{15 \times 1}} = 20{\text{ day}} \cr} $$
5
If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
Discuss
Answer & Solution
Answer: Option C
Solution:
27 × 8 × 12 = 18 × 9 × x
x = 16 days
6
A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in∶
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
7
A can complete work in 25 days and B can complete the same work in 20 days. They started the work together but B left after 4 days and A continued to work. In how many days will the entire work be completed?
Discuss
Answer & Solution
Answer: Option B
Solution:
Time and Work mcq question image
Total work of (A + B) in 4 days = 4(4 + 5) = 36
Remaining work = 100 - 36 = 64
A = $$\frac{{64}}{4}$$ = 16 days
Total days = 4 + 16 = 20 days
8
P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two-third part of the same work?
Discuss
Answer & Solution
Answer: Option A
Solution:
Time and Work mcq question image
Efficiency of Q = 2
So, required answer = $$\frac{{36 \times \frac{2}{3}}}{2}$$  = 12 days
9
A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & 45\% = \frac{9}{{20}} \cr & {\text{Efficiency A}} = 29{\text{ and B}} = 20 \cr & 58 \times 49 + 29 \times 20 = 3422 \cr & {\text{Required answer A}} = \frac{{3422}}{{29}} = 118\,{\text{days}} \cr} $$
10
20 man can finish a work in 30 days. They started working, but 4 men left the work after 10 days. In how many days would the work be completed?
Discuss
Answer & Solution
Answer: Option C
Solution:
Total work = 30 × 20 = 600
After 10 days = 20 × 10 = 200
Remaining work = 600 - 200 = 400
4 men left, remaining = 16 men
16 × D = 400
D = $$\frac{{400}}{{16}}$$
D = 25 days
Total days = 25 + 10 = 35 days