A company has three mines at locations A, B and C, which supply coal to power plants at D, E, F and G. Mines A, B and C produce 1800 t/day, 1700 t/day, and 2900 t/day respectively. Daily raw coal requirements at the power plants D, E, F and G from these mines are 2050 t, 1600 t, 1300 t, and 1450 t respectively. Unit transportation costs are as follows:
Mines ↓ Power Plants
D E F G
A 3.5 4.0 2.5 5.5
B 4.5 3.7 6.0 4.7
C 4.2 3.8 5.2 2.9
The company has to minimize the total cost of transportation to the power plants. The problem is

Answer & Solution
Correct Answer: Option B
Let's discuss the solution. Join the discussion