The failure data analysis of a longwall mining system consisting of thre major subsystems revealed that the failure rate of shearer, face conveyor any stage loader are 0.15/ hour, 0.2/ hour and 0.1/ hour respectively. If all the subsystems must be running for a satisfactory system operation, the reliability of the longwall system for a period of 4 hours is
A. 0.165
B. 0.259
C. 0.405
D. 0.63
Answer: Option A