Examveda
Examveda

A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1 - 2 1 1 7
1 - 3 2 5 8
2 - 4 1 1 7
3 - 4 2 5 14
4 - 5 3 6 15

The expected duration of the mining project in months is

A. 5

B. 16

C. 18

D. 29

Answer: Option C


This Question Belongs to Mining Engineering >> Mine System Engineering

Join The Discussion

Related Questions on Mine System Engineering