Mine System Engineering
?

A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1 - 2 1 1 7
1 - 3 2 5 8
2 - 4 1 1 7
3 - 4 2 5 14
4 - 5 3 6 15
The expected duration of the mining project in months is

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion