A mining project is composed of five activities whose three time estimates in months are given below:
Activity | Estimated duration (months) | ||
Optimistic time | Most likely time | Permissible time | |
1 - 2 | 1 | 1 | 7 |
1 - 3 | 2 | 5 | 8 |
2 - 4 | 1 | 1 | 7 |
3 - 4 | 2 | 5 | 14 |
4 - 5 | 3 | 6 | 15 |
The expected duration of the mining project in months is
A. 5
B. 16
C. 18
D. 29
Answer: Option C