Workmen arrive at a mine workshop to receive tools for maintenance. The inter-arrival time of workmen at the service counter is exponentially distributed with an average time of 10 min. The service time at the counter is also distributed exponentially with a mean time of 6 min. The average time spent by a workman waiting for his turn to be served in min is
A. 9
B. 12
C. 15
D. 18
Answer: Option A