A job is budgeted to require 3,300 productive hours after incurring 25% idle time. If the total labour cost budgeted for the job is Rs 36,300. What is the labour cost per hour( to the nearest cent)?

A. Rs 8.25

B. Rs 8.80

C. Rs 11.00

D. Rs 14.67

Answer: Option A


This Question Belongs to Commerce >> Costing

Join The Discussion

Comments ( 2 )

  1. Naresh Kumar
    Naresh Kumar :
    6 years ago

    3300*100/75=4400

    36300/4400=8.25