A mining machinery company has four plants at locations A, B, C, and D and three warehouses at destinations X, Y and Z. The number of machine units available at the plants A, B, C and D are 5, 8, 7 and 14 respectively. The demands at X, Y and Z are 7, 9 and 18 respectively. The unit costs of transportation in rupees as follows:
Destinations
X Y Z
Locations A 20 70 40
B 30 30 10
C 50 40 70
D 10 60 20
The total cost of transportation in rupees based on the initial basic feasible solution obtained by the north-west corner rule is

Answer & Solution
Correct Answer: Option C