Examveda
Examveda

A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1-2 1 1 7
1-3 2 5 8
2-4 1 1 7
3-4 2 5 14
4-5 3 6 15
The standard deviation of the project length in months is

A. 2

B. 3

C. 6

D. 9

Answer: Option B


This Question Belongs to Mining Engineering >> Mine System Engineering

Join The Discussion

Related Questions on Mine System Engineering