ExamVeda
Login
Home
Mine System Engineering
?

A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1-2 1 1 7
1-3 2 5 8
2-4 1 1 7
3-4 2 5 14
4-5 3 6 15
The standard deviation of the project length in months is

Answer & Solution
Correct Answer: Option B
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

No comments yet Be the first to discuss this question.