A mining project is composed of five activities whose three time estimates
in months are given below:
Activity | Estimated duration (months) | ||
Optimistic time | Most likely time | Permissible time | |
1-2 | 1 | 1 | 7 |
1-3 | 2 | 5 | 8 |
2-4 | 1 | 1 | 7 |
3-4 | 2 | 5 | 14 |
4-5 | 3 | 6 | 15 |
A. 2
B. 3
C. 6
D. 9
Answer: Option B