A workshop has four machines for assigning four jobs. Each job can be assigned to only one machine. Estimated processing cost (in Rs.) at each machine to complete each task is given in the table below
| Machine | |||||
| M1 | M2 | M3 | M4 | ||
| Tasks | T1 | 61 | 92 | 52 | 72 |
| T2 | 42 | 49 | 69 | 85 | |
| T3 | 47 | 59 | 80 | 71 | |
| T4 | 65 | 70 | 68 | 72 | |
A. 214
B. 220
C. 215
D. 262
Answer: Option B