Activity durations in PERT and CPM are decided on the following consideration
A. PERT - stochastic, CPM - deterministic
B. PERT - stochastic, CPM - stochastic
C. PERT - deterministic, CPM - deterministic
D. PERT - deterministic, CPM - stochastic
Answer: Option A