Activity durations in PERT and CPM are decided on the following consideration

A. PERT - stochastic, CPM - deterministic

B. PERT - stochastic, CPM - stochastic

C. PERT - deterministic, CPM - deterministic

D. PERT - deterministic, CPM - stochastic

Answer: Option A


This Question Belongs to Mining Engineering >> Mine System Engineering