ExamVeda
Login
Home
11
To do a certain work, the ratio of efficiency of A to that of B is 3 : 7. Working together, they can complete the work in $$10\frac{1}{2}$$ days. They work together for 8 days. 60% of the remaining work will be completed by A alone in:
Discuss
Answer & Solution
Answer: Option C
Solution:
\[\begin{array}{*{20}{c}} {}&A&{}&B \\ {{\text{Efficiency}} \to }&3&:&7 \end{array}\]
$$\eqalign{ & {\text{Total work}} = \left( {3 + 7} \right) \times \frac{{21}}{2} = 105 \cr & \left( {A + B} \right) \times 8 = \left( {3 + 7} \right) \times 8 = 80 \cr & {\text{Remaining work}} = 105 - 80 = 25 \cr & 60\% {\text{ work done by }}A = \frac{{25 \times 60}}{{100 \times 3}} = 5{\text{ days}} \cr} $$
12
3 men and 4 women can do a piece of work in 7 days, whereas 2 men and 1 woman can do it in 14 days. 7 women will complete the same work in:
Discuss
Answer & Solution
Answer: Option A
Solution:
(3m + 4w) × 7 = (2m + 1w) × 14
3m + 4w = 4m + 2w
m = 2w
m : w = 2 : 1
Total work = (3 × 2 + 4 × 1) × 7 = 70 unit
7w = 70 unit = $$\frac{{70}}{7}$$ = 10 days
13
To do a certain work, the ratio of the efficiencies of X and Y is 5 : 4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in:
Discuss
Answer & Solution
Answer: Option A
Solution:
\[\begin{array}{*{20}{c}} {}&{\text{X}}&{}&{\text{Y}} \\ {{\text{Efficiency}}}&5&:&4 \end{array}\]
Total work = (5 + 4) × 10 = 90
Y × 5 + X × a = 90
4 × 5 + 5 × a = 90
20 + 5a = 90
5a = 70
a = 14
14
A contractor decided to complete a work in 80 days and employed 60 men at the beginning and 20 men additionally after 20 days and got the work completed as per schedule. If he had not employed, the additional men, how many extra days would he have needed to complete the work (round off to the nearest integer)?
Discuss
Answer & Solution
Answer: Option B
Solution:
Total work = 80 × 60 + 60 × 20
= 4800 + 1200
= 6000
60 men × d = 6000
d = 100 days
Extra days = 100 - 80 = 20 days
15
A can do piece of work in 15 days. B is 25% more efficient than A, and C is 40% more efficient than B, A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:
Discuss
Answer & Solution
Answer: Option A
Solution:
\[\begin{array}{*{20}{c}} {}&\begin{gathered} {\text{A}}\,\,\,\,\,\,{\text{B}}\,\,\,\,\,\,{\text{C}} \hfill \\ {\text{4}}\,\,\,{\text{:}}\,\,\,{\text{5}}\,\,\,{\text{:}}\,\,\,{\text{7}} \hfill \\ {\text{5}}\,\,\,{\text{:}}\,\,\,{\text{7}}\,\,\,\,\,\,\,\,\,\, \hfill \\ \end{gathered} \\ {{\text{Efficiency}} \to }&{\overline {\,4\,:\,5\,:\,7\,} } \end{array}\]
Total work = 4 × 15 = 60 units
(A + C) × 3 + (A + B)x = 60
11 × 3 + 9 × x = 60
33 + 9x = 60
9x = 27
x = 3 days
16
A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find the how many days B alone can do the work?
Discuss
Answer & Solution
Answer: Option A
Solution:
Time and Work mcq question image
A : C = 2 : 1
A = 4 unit
C = 2 unit
B = 1 unit
B = $$\frac{{90}}{1}$$ = 90 days
17
To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in $$17\frac{1}{2}$$ days. A alone will complete 60% of the same work in:
Discuss
Answer & Solution
Answer: Option A
Solution:
\[\begin{array}{*{20}{c}} {}&{\text{A}}&:&{\text{B}} \\ {{\text{Efficiency}}}&7&:&5 \end{array}\]
$$\eqalign{ & {\text{A}} + {\text{B}} = 12 \times \frac{{35}}{2} = 35 \times 6{\text{ Total work}} \cr & {\text{A}} = \frac{{35 \times 6 \times \frac{3}{5}}}{7} = 18{\text{ days}} \cr} $$
18
A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in:
Discuss
Answer & Solution
Answer: Option C
Solution:
\[\begin{array}{*{20}{c}} {}&A&:&{B + C}&{}&{} \\ {{\text{Efficiency}} \to }&{{1_{ \times 4}}}&:&{{1_{ \times 4}}}& \Rightarrow &{{2_{ \times 4}}} \\ {}&{A + B}&:&C&{}&{} \\ {{\text{Days}} \to }&{36}&:&{60}&{}&{} \\ {{\text{Efficiency}} \to }&5&:&3& \Rightarrow &8 \\ {{\text{Efficiency}} \to }&A&:&B&:&C \\ {}&4&:&1&:&3 \end{array}\]
$$\eqalign{ & {\text{Total work}} = 3 \times 60 = 180 \cr & \left( {A + C} \right) \times 10 + B \times x = 180 \cr & 7 \times 10 + 1 \times x = 180 \cr & x = 110{\text{ Days}} \cr} $$
19
A, B and C can complete a piece of work separately in 10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?
Discuss
Answer & Solution
Answer: Option A
Solution:
Time and Work mcq question image
A's three days work = 4 × 3 = 12
B and C one day work = 3 × 1 = 3
A, B, C three days work = 15 unit
A, B, C six days work = 30 unit
7th day work = 4 unit
8th day work = 4 unit
Total = 38 unit
Work left 2 unit
7 units in 1 days
2 units in $$\frac{2}{7}$$ days
Total time = $$8\frac{2}{7}$$ days
20
A tyre has 3 punctures. The first puncture alone would have made the tyre flat in 9 minutes, the second alone would have done it in 18 minutes, the third alone would have done it in 6 minutes. If the air leaks out at a constant rate, then how long (in minutes) does it take for all the punctures together to make it flat?
Discuss
Answer & Solution
Answer: Option D
Solution:
Time and Work mcq question image
$$\therefore \frac{{18}}{{2 + 1 + 3}} = 3{\text{ minutes}}$$