ExamVeda
Login
Home
21
A certain number of persons can complete a work in 34 days working 9 h a day. If the number of persons is decreased by 40%. Then how many hours a day should the remaining persons work to complete the work in 51 days?
Discuss
Answer & Solution
Answer: Option B
Solution:
\[40\% \to \frac{{ - 2}}{5}\begin{array}{*{20}{c}} {} \\ { \to \,{\text{Men}}} \end{array}\]
$$\eqalign{ & 9 \times 34 \times 5 = 3 \times 51 \times x \cr & x = 10{\text{ hours}} \cr} $$
22
There are 3 taps A, B, and C in a tank. These can fill the tank in 10 hours, 20 hours and 25 hours, respectively. At first, all three taps are opened simultaneously. After 2 hours, tap C is closed and A and B keep running. After 4 hours from the beginning, tap B is also closed. The remaining tank is filled by tap A alone. Find the percentage of work done by tap A itself.
Discuss
Answer & Solution
Answer: Option D
Solution:
Time and Work mcq question image
2 hours total → 2 × 19 = 38
4 hours total = 38 + 2 × 15 = 68
Remaining work = 100 - 68 = 32
Total work done by A = 32 + 40 = 72
Required % = $$\frac{{72}}{{100}}$$ × 100 = 72%
23
P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in $$\frac{{13}}{5}$$ days, then in how many days can Q alone finish $$66\frac{2}{3}\% $$  of the same work?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & {\text{Total work}} = 18P = 5P + \frac{{13}}{5}\left( {P + Q} \right) \cr & 13P = \frac{{13}}{5}P + \frac{{13}}{5}Q \cr & \frac{{52}}{5}P = \frac{{13}}{5}Q \cr & \frac{P}{Q} = \frac{1}{4} \cr & {\text{Total work}} = 18 \times 1 = 18 \cr & 66\frac{2}{3}\% {\text{ of work}} = \frac{2}{3} \times 18 = 12 \cr & Q{\text{ days}} = \frac{{12}}{4} = 3{\text{ days}} \cr} $$
24
A man, a woman and a boy can complete a work in 3, 4 and 12 days, respectively. How many boys must assist one man and one woman to complete the same work in one day?
Discuss
Answer & Solution
Answer: Option A
Solution:
Time and Work mcq question image
Total work for 1Men + 1Women + xBoy in 1 day = 12
⇒ 1 × 4 + 1 × 3 + 1 × x = 12
⇒ x = 12 - 7
⇒ x = 5
25
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?
Discuss
Answer & Solution
Answer: Option C
Solution:
(5M + 8W) × 34 = (4M + 18W) × 28
85M + 136W = 56M + 252W
29M = 116W
$$\frac{{\text{M}}}{{\text{W}}} = \frac{4}{1}$$
(5M + 8W) × 34 = (3M + 5W) × x
(5 × 4 + 8 × 1) × 34 = (3 × 4 + 5 × 1) × x
28 × 34 = 17 × x
x = 56 days
26
B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let A completes the work in $$x$$ hours
∴ B completes the work in $$x$$ + 10 hours
Time and Work mcq question image
⇒ A + B complete the work in 12 hours
$$\eqalign{ & \therefore \frac{{x\left( {10 + x} \right)}}{{10 + x + x}} = 12 \cr & 10x + {x^2} = 120 + 24x \cr & {x^2} - 14x - 120 = 0 \cr} $$
On solving, $$x$$ = 20 hours
∴ B will complete whole work in 20 + 10 = 30 hours
Hence, 50% of work will be completed in 15 hours
27
Smith and Ajit can complete a task in 12 days and 18 days, respectively. If they work together on the task for 4 days, then the fraction of the task that will be left is:
Discuss
Answer & Solution
Answer: Option D
Solution:
Time and Work mcq question image
(Smith + Ajit) × 4 = 4 × 5 = 20
Remaining work = 36 - 20 = 16
Then the fraction of the task that will be left is $$ = \frac{{16}}{{36}} = \frac{4}{9}$$
28
If 6 women can complete a work in 3 days, and 9 girls can complete the same work in 2 days, then find the time taken to complete the same work by 8 women and 6 girls?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & 6W \times 3 = 9G \times 2 \cr & \frac{W}{G} = \frac{1}{1} \cr & {\text{Total work}} = 18 \cr & 18 = \left( {8W + 6G} \right) \times d \cr & 18 = 14 \times d \cr & d = \frac{9}{7}{\text{ days}} \cr} $$
29
A, B and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?
Discuss
Answer & Solution
Answer: Option B
Solution:
Time and Work mcq question image
If B worked 5 days more = 3 × 5 = 15 unit
If C worked 10 days more = 2 × 10 = 20 unit
Now, total work = 108 + 15 + 20 = 143
(A + B + C) = $$\frac{{143}}{{11}}$$ = 13 days
30
Amir and Akbar can finish a task in 30 days and 15 days, respectively. Akbar worked on the task for 8 days and left the job. In how many days can Amir alone finish the remaining work?
Discuss
Answer & Solution
Answer: Option A
Solution:
Time and Work mcq question image
Akbar's 8 days work = 8 × 2 = 16
Remaining work = 30 - 16 = 14