ExamVeda
Login
Home
41
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?
Discuss
Answer & Solution
Answer: Option C
Solution:
According to the question,
3 men = 5 women
As they complete the same work in same time
6 men + 5 women
= 6 men + 3 men
= 9 men
If, 3 men does a work in 12 days
1 men does a work in 12 × 3
9 men does a work in $$\frac{{{\text{12}} \times {\text{3}}}}{9}$$  = 4 days

Alternate :
$$\eqalign{ & 3{\text{ men}} \times {\text{12}} = {\text{5 women}} \times {\text{12}} \cr & \frac{{{\text{men}}}}{{{\text{women}}}} = \frac{5}{3} \cr & {\text{Total work}} \cr & = 3 \times 5 \times 12 \cr & = 15 \times 12 \cr & = 180{\text{ units}} \cr & {\text{Efficiency of 6 men}} + {\text{5 women}} \cr & = 6 \times 5 + 5 \times 3 \cr & = 45 \cr & {\text{Time taken by 6 men}} + {\text{5 women}} \cr & = \frac{{180}}{{45}} \cr & = 4{\text{ days}} \cr} $$
42
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & {\text{10 men}} \times {\text{12 days}} = {\text{10 women}} \times {\text{6 days}} \cr & {\text{2 men}} = {\text{1 woman}} \cr & \frac{{\text{M}}}{{\text{W}}} = \frac{1}{2}{\text{ }} \cr & {\text{1 man work}} = {\text{1 unit/day}} \cr & {\text{1 woman work}} = {\text{2 unit/day}} \cr & {\text{Total work}} = {\text{10 men}} \times {\text{12 days}} \cr & = 10 \times 1 \times 12 \cr & = 120{\text{ units}} \cr & {\text{Time required}}\left( {{\text{10 men}} + {\text{10 women}}} \right) \cr & = \frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{120}}{{10 \times 1 + 10 \times 2}} \cr & = \frac{{120}}{{30}} \cr & = 4{\text{ days}} \cr} $$
43
Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Let A and B together take x hours to complete the work.
Then, A alone takes (x + 8) hours
And
B alone takes $$\left( {{\text{x}} + \frac{9}{2}} \right)$$   hours to complete the work
Then,
$$\eqalign{ & \Rightarrow \frac{1}{{\left( {x + 8} \right)}} + \frac{1}{{\left( {x + \frac{9}{2}} \right)}} = \frac{1}{x} \cr & \Rightarrow \frac{1}{{\left( {x + 8} \right)}} + \frac{2}{{\left( {2x + 9} \right)}} = \frac{1}{x} \cr & \Rightarrow x\left( {4x + 25} \right) = \left( {x + 8} \right)\left( {2x + 9} \right) \cr & \Rightarrow 2{x^2} = 72 \cr & \Rightarrow {x^2} = 36 \cr & \Rightarrow x = 6 \cr} $$
44
Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Let the time taken by the three friends together to do the work be x hours
Then, time taken by Anne alone = (x + 6) hours
Time taken by Bob alone = (x + 1) hours
Time taken by Bob alone = 2x hours
$$\therefore \frac{1}{{x + 6}} + \frac{1}{{x + 1}} + \frac{1}{{2x}} = \frac{1}{x}$$
$$ \Rightarrow $$ $$\frac{{2x\left( {x + 1} \right) + 2x\left( {x + 6} \right) + \left( {x + 1} \right)\left( {x + 6} \right)}}{{2x\left( {x + 6} \right)\left( {x + 1} \right)}}$$         $$ = $$ $$\frac{1}{x}$$
$$\eqalign{ & \Rightarrow 5{x^2} + 21x + 6 = 2\left( {{x^2} + 7x + 6} \right) \cr & \Rightarrow 3{x^2} + 7x - 6 = 0 \cr & \Rightarrow \left( {x + 3} \right)\left( {3x - 2} \right) = 0 \cr & \Rightarrow x = \frac{2}{3}{\text{ }}\left[ {\because x \ne - 3} \right] \cr & \therefore {\text{Required times}} \cr & = \frac{2}{3}{\text{ hours}} \cr & = \left( {\frac{2}{3} \times 60} \right){\text{hours}} \cr & = 40{\text{ minutes}} \cr} $$
45
A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{{12}} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{8} \cr & \left( {{\text{A}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{{16}} \cr} $$
Adding, we get 2(A + B + C)'s 1 day's work
$$\eqalign{ & = \left( {\frac{1}{{12}} + \frac{1}{8} + \frac{1}{{16}}} \right) \cr & = \frac{{13}}{{96}} \cr} $$
So, A, B and C together can complete the work in
$$\eqalign{ & = \frac{{96}}{{13}} \cr & = 7\frac{5}{{13}}{\text{days}} \cr} $$
46
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & {\text{Let additional men be }}x \cr & \frac{{25 \times 24}}{{{\text{Work}} \to \frac{1}{3}}} = \frac{{\left( {25 + x} \right) \times 12}}{{\frac{2}{3}\left( {{\text{Remaining work 1}} - \frac{1}{3}} \right)}} \cr & \Rightarrow x = 75 \cr} $$
47
639 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & {\text{According to the question,}} \cr & {\text{Let, D is number of days}} \cr & \frac{{639 \times 12 \times 5}}{{1{\text{ road}}}} = \frac{{30 \times 6 \times {\text{D}}}}{{1{\text{ road}}}} \cr & \Leftrightarrow {\text{D}} = {\text{213 days}} \cr} $$
48
If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & {\text{Here work is 280 m length of wall }} \cr & {\text{And 100 m length of wall}} \cr & {\text{Let, M men will finish 100 m wall}}{\text{.}} \cr & \frac{{72 \times 21}}{{280}} = \frac{{{\text{M}} \times {\text{18}}}}{{100}} \cr & \Leftrightarrow {\text{M}} = 30 \cr} $$
49
4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & \frac{{{4_{{\text{mat - wevers}}}} \times {4_{{\text{days}}}}}}{{{4_{{\text{mats}}}}}} = \frac{{{8_{{\text{mat - wevers}}}} \times {8_{{\text{days}}}}}}{{{{\text{N}}_{{\text{mats}}}}}} \cr & \Leftrightarrow {\text{N}} = {\text{16 mats}} \cr} $$
50
A can do a piece of work in 4 hours, B and C together in 3 hours, and A and C together in 2 hours. How long will B alone take to do it ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & {\text{A's 1 hour's work}} = \frac{1}{4} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 hour's work}} = \frac{1}{3} \cr & \left( {{\text{A}} + {\text{C}}} \right){\text{'s 1 hour's work}} = \frac{1}{2} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 hour's work}} \cr & = \frac{1}{4} + \frac{1}{3} \cr & = \frac{7}{{12}} \cr & \therefore {\text{B's 1 hour's work}} \cr} $$
= (A + B + C)'s 1 hour's work - (A + C)'s 1 hour's work
$$\eqalign{ & = \frac{7}{{12}} - \frac{1}{2} \cr & = \frac{1}{{12}} \cr} $$
So, B alone can complete the work in 12 hours.