ExamVeda
Login
Home
51
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{6} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{8} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{{12}}{\text{ }} \cr & \therefore \left( {{\text{A}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {2 \times \frac{1}{6}} \right) - \left( {\frac{1}{8} + \frac{1}{{12}}} \right) \cr & = \left( {\frac{1}{3} - \frac{5}{{24}}} \right) \cr & = \frac{3}{{24}} \cr & = \frac{1}{8} \cr} $$
So, A and C together will do the work in 8 days.
52
A and B together can do a job in 2 days; B and C can do it in 4 days; A and C in $${\text{2}}\frac{2}{5}$$ days. The number of days required for A to do the job alone is = ?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{2} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{4} \cr & \left( {{\text{A}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{5}{{12}} \cr & {\text{Adding, we get: }} \cr & {\text{2}}\left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{2} + \frac{1}{4} + \frac{1}{{12}}} \right) \cr & = \frac{{14}}{{12}} \cr & = \frac{7}{6} \cr & \Rightarrow \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{7}{{12}} \cr & {\text{So, A's 1 day's work}} \cr & = \left( {\frac{7}{{12}} - \frac{1}{4}} \right) \cr & = \frac{4}{{12}} \cr & = \frac{1}{3} \cr & \therefore {\text{A alone can do the work in 3 days}}{\text{.}} \cr} $$
53
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & \frac{{{{10}_{{\text{men}}}} \times {6_{{\text{hours}}}} \times {{18}_{{\text{days}}}}}}{{{1_{{\text{work}}}}}} = \frac{{{{15}_{{\text{men}}}} \times {{12}_{{\text{days}}}} \times {\text{H hour/day}}}}{{{1_{{\text{work}}}}}} \cr & \Leftrightarrow {\text{6 hours/day}} \cr} $$
54
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let total number of worker in beginning is N
$$\eqalign{ & {\text{According to the question,}} \cr & \frac{{{\text{N}} \times {{100}_{{\text{days}}}}}}{{{1_{{\text{work}}}}}} = \frac{{\left( {{\text{N}} - 10} \right) \times {{110}_{{\text{days}}}}}}{{{1_{{\text{work}}}}}} \cr & 100{\text{N}} = {\text{110N}} - {\text{1100}} \cr & \Rightarrow {\text{10N}} = {\text{1100}} \cr & \Rightarrow {\text{N}} = {\text{110}} \cr} $$
55
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Discuss
Answer & Solution
Answer: Option B
Solution:
According to the question,
Total work
= 12 M × 12 D
= 144 units
Work done by 12 men in 6 days
= 12 × 6
= 72 units
Rest work
= 144 - 72
= 72 units
Required time for 6 men to complete the work
$$\eqalign{ & = \frac{{72}}{6} \cr & {\text{ = 12 days}} \cr & {\text{Hence,}} \cr & {\text{Total time}} = 12 + 6 = 18{\text{ days}} \cr & {\text{Extra time}} = 18 - 12 = 6{\text{ days}} \cr} $$
56
60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?
Discuss
Answer & Solution
Answer: Option B
Solution:
60 men work for 200 days.
They stops for 10 day due to bad weather.
So, the work is to complete in
= (50 - 10)
= 40 days
In order to complete in scheduled time i.e., 250 days.
Let 'n' number of more men is required
(60men × 200days) +{(60 + n)men × 40days} = 60men × 250days
⇒ 12000 + {(60 + n)men × 40days} = 15000
⇒ (60 + n)40days = 3000
⇒ 60 + n = 75
⇒ n = 15

Alternate :
60 men can complete a work in 250 days.
But they work for 200 days.
Then remaining days = 50 days
So,
60 × 50 = 60 + x × 40
⇔ x = 15
57
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{{12}} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{8} \cr & \left( {{\text{A}} + {\text{C}}} \right){\text{'s 1 day's work}} = \frac{1}{{62}} \cr} $$
[ (A + B)'s 1 day's work + (B + C)'s 1 day's work ] - (A + C)'s 1 day's work
$$\eqalign{ & = \frac{1}{{12}} + \frac{1}{8} - \frac{1}{6} \cr & \Rightarrow 2\left( {{\text{B's 1 day's work}}} \right) = \frac{1}{{24}} \cr & \Rightarrow {\text{B's 1 day's work}} = \frac{1}{{48}} \cr} $$
Hence, B alone can do the work in 48 days.
58
A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{{25}} \cr & {\text{C's 1 day's work}} = \frac{1}{{35}} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{25}} + \frac{1}{{35}}} \right) \cr & = \frac{{12}}{{175}}.....({\text{i}}) \cr} $$
Also, A's 1 day's work = (B + C)'s 1 day's work.....(ii)
$$\eqalign{ & {\text{From (i) and (ii), we get : }} \cr & \Rightarrow {\text{2}} \times \left( {{\text{A's 1 day's work}}} \right) = \frac{{12}}{{175}} \cr & \Rightarrow {\text{A's 1 day's work}} = \frac{6}{{175}} \cr & \therefore {\text{B's 1 day's work}} \cr & = \left( {\frac{1}{{25}} - \frac{6}{{175}}} \right) \cr & = \frac{1}{{175}} \cr} $$
59
Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Suppose Uma takes x days to complete a work
Then, Madhu takes 2x days to complete the work
Uma's 1 day's work = $$\frac{1}{x}$$
Madhu's 1 day's work = $$\frac{1}{{2x}}$$
Rahul's 1 day's work = (Madhu + Uma)'s 1 day's work
$$\eqalign{ & = \frac{1}{{2x}} + \frac{1}{x} \cr & = \frac{3}{{3x}}{\text{ }} \cr} $$
(Madhu + Uma + Rahul)'s 1 day's work
$$\eqalign{ & = \frac{3}{{3x}} + \frac{1}{{2x}} + \frac{1}{x} = \frac{6}{{3x}} = \frac{3}{x} \cr & \therefore \frac{3}{x} = \frac{1}{6} \cr & \Rightarrow x = 18{\text{ }} \cr} $$
Hence, Madhu takes (2 × 18) = 36 days to complete the work
60
If 28 men complete $$\frac{7}{8}$$ of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & \frac{{{\text{28 M}} \times {\text{1 Week}}}}{{\frac{7}{8}}} = \frac{{x \times {\text{ 1 Week}}}}{{\frac{1}{8}}} \cr & \Leftrightarrow x = 4{\text{ men}} \cr} $$