ExamVeda
Login
Home
51
12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?
Discuss
Answer & Solution
Answer: Option B
Solution:
12 men can do a piece of work in 24 days
$$ \Rightarrow {{\text{M}}_1} = 12{\text{ and }}{{\text{D}}_1} = 24$$
8 men can do this work in $${{\text{D}}_2}$$ days
$$\eqalign{ & \Rightarrow {{\text{M}}_2} = 8{\text{ }} \cr & \,\,\,\,\,\,\,\,\,{{\text{M}}_1}{{\text{D}}_1} = {{\text{M}}_{\text{2}}}{{\text{D}}_{\text{2}}} \cr & \Rightarrow 12 \times 24 = 8 \times {{\text{D}}_2} \cr & \Rightarrow {{\text{D}}_2} = \frac{{12 \times 24}}{8} \cr & \Rightarrow {{\text{D}}_2} = 36{\text{ days}} \cr} $$
52
A can do in one day three times the work done by B in one day. They together finish $$\frac{2}{5}$$ of the work in 9 days. The number of days by which B can do the work alone is = ?
Discuss
Answer & Solution
Answer: Option A
Solution:
Let time taken by A alone in doing work be x days
∴ Time taken by B alone = 3x days
$$\eqalign{ & {\text{A's 1 day's work}} = \frac{1}{x} \cr & {\text{B's 1 days work}} = \frac{1}{{3x}} \cr & \because {\text{A and B together finish}} \cr & = \frac{2}{5}{\text{work in 9 days}}{\text{.}} \cr} $$
∴ Time taken by A and B in doing whole work
$$\eqalign{ & = \frac{{9 \times 5}}{2} \cr & = \frac{{45}}{2}{\text{ days}} \cr} $$
According to given information we get
$$\eqalign{ & \therefore \frac{1}{x} + \frac{1}{{3x}} = \frac{2}{{45}} \cr & \Rightarrow \frac{{3 + 1}}{{3x}} = \frac{2}{{45}} \cr & \Rightarrow \frac{4}{{3x}} = \frac{2}{{45}} \cr & {\text{By cross - multiply we get }} \cr & \Rightarrow 2 \times 3x = 4 \times 45 \cr & \Rightarrow x = \frac{{4 \times 45}}{{2 \times 3}} \cr & \Rightarrow x = 30{\text{ days}} \cr & {\text{Time taken by A}} \cr & = x{\text{ days}} \cr & = {\text{30 days}} \cr & \therefore {\text{Time taken by B}} \cr & = 3x{\text{ days}} \cr & = 3 \times 30 \cr & = 90{\text{ days}} \cr} $$
53
A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{A's 1 day's work}} = \frac{1}{{24}} \cr & {\text{B's 1 day's work}} = \frac{1}{5} \cr & {\text{C's 1 day's work}} = \frac{1}{{12}} \cr & \therefore \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \frac{1}{{24}} + \frac{1}{5} + \frac{1}{{12}} \cr & {\text{L}}{\text{.C}}{\text{.M of 24, 5 and 12}} \cr} $$
2     24 - 5 - 12
2     12 - 5 - 6
3     6 - 5 - 3
    2 - 5 - 1
$$\eqalign{ & {\text{2}} \times 2 \times 3 \times 2 \times 5 = 120 \cr & = \frac{{5 + 24 + 10}}{{120}} \cr & = \frac{{39}}{{120}} \cr & = \frac{{13}}{{40}} \cr} $$
Time taken by A, B and C to complete the work, working together
$$\eqalign{ & = \frac{{40}}{{13}} \cr & = 3\frac{1}{{13}}{\text{days}} \cr} $$
54
If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{According to the question,}} \cr & \Rightarrow {\text{4m}} + {\text{6w}} = 8{\text{ days}}.....{\text{(i)}} \cr & {\text{or}} \cr & \Rightarrow {\text{32m}} + 48{\text{w}} = 1{\text{ days}} \cr & \Rightarrow {\text{3m}} + 7{\text{w}} = 10{\text{ days}}.....{\text{(ii)}} \cr & {\text{or}} \cr & \Rightarrow {\text{30m}} + 70{\text{w}} = 1{\text{ day}} \cr & \therefore {\text{32m}} + {\text{48w}} = 30{\text{m}} + 70{\text{w}} \cr & \Rightarrow {\text{2m}} = 22{\text{w}} \cr & \Rightarrow {\text{m}} = 11{\text{w}} \cr & {\text{From (i)}} \cr & \Rightarrow {\text{4m}} = 44{\text{w}} \cr & \therefore \left( {{\text{44w}} + {\text{6w}}} \right) \times 8 = 10{\text{w}} \times x \cr & \Rightarrow {\text{50w}} \times 8 = 10{\text{w}} \times x \cr & \Rightarrow x = 40{\text{ days}} \cr} $$
55
A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Days     Eff.     Total work
     
A - 12   2  
    24
B - 12   1  
  3  
     

A and B together can finish the work
$$\eqalign{ & = \frac{{24}}{3} \cr & = 8{\text{ days}} \cr} $$
56
Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?
Discuss
Answer & Solution
Answer: Option D
Solution:
  Amit     Bhawana     Chandan
Eff. →   5x x 2x

$$\eqalign{ & {\text{Let total work}} = 1 \cr & {\text{Efficiency of }}\left( {{\text{A}} + {\text{B}} + {\text{C}}} \right) = 1 \cr & {\text{Then,}} \cr & \Leftrightarrow 5x + x + 2x = 1 \cr & \Leftrightarrow x = \frac{1}{8} \cr & {\text{Days taken by Amit}} \cr & = \frac{1}{{\frac{5}{8}}} \Rightarrow \frac{8}{5} \cr & {\text{Days taken by Chandan}} \cr & = \frac{1}{{\frac{2}{8}}} \Rightarrow 4 \cr & {\text{Difference of days}} \cr & = 4 - \frac{8}{5} \Rightarrow \frac{{20 - 8}}{5} \Rightarrow 2\frac{2}{5} \cr} $$
57
12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?
Discuss
Answer & Solution
Answer: Option A
Solution:
12 man × 15 = 20 women × 12 = Total work
3 man = 4 women
$$\eqalign{ & \frac{{{\text{Men}}}}{{{\text{Women}}}} = \frac{4}{3} \to {\text{Efficiency}} \cr & {\text{Total work}} = 12 \times 4 \times 15 = 720 \cr & \left( {5{\text{ man}} + 5{\text{ women}}} \right) \times {\text{D}} = 720 \cr & {\text{D}}\left( {5 \times 4 + 5 \times 3} \right) = 720 \cr & {\text{D}} = \frac{{720}}{{35}} = 20\frac{4}{7}{\text{ days}} \cr} $$
Alternate:
According to the question,
12 men can do the 1 day work in $$\frac{1}{{15}}$$ days
So, 1 men can do the 1 day work in $$\frac{1}{{15 \times 12}}$$  = $$\frac{1}{{180}}$$ days
5 men can do the 1 day work in $$\frac{1}{{180}} \times 5$$   = $$\frac{5}{{180}}$$ days
Similarly 5 women do the 1 dys work $$\frac{5}{{240}}$$ days
∴ 5 men & 5 women together work in 1 day
$$\eqalign{ & = \frac{5}{{180}} + \frac{5}{{240}} \cr & = \frac{{20 + 15}}{{720}} \cr & = \frac{{35}}{{720}} \cr} $$
Hence, they complete the work $$\frac{{720}}{{35}}$$ = $$20\frac{4}{{35}}$$ days
58
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & {\text{X's 1 day's work}} = \frac{1}{{24}} \cr & {\text{X's 16 day's work}} = \frac{{16}}{{24}} \cr & {\text{Let,}} \cr} $$
Y alone complete the work in x days
$${\text{Y's 12 day's work}} = \frac{{12}}{x}$$
According to the question,
Complete work done by X and Y = 1
X's 16 day's work + Y's 12 day's work = 1
$$\eqalign{ & \Rightarrow \frac{{16}}{{24}} + \frac{{12}}{x} = 1 \cr & \Rightarrow \frac{2}{3} + \frac{{12}}{x} = 1 \cr & \Rightarrow \frac{{12}}{x} = 1 - \frac{2}{3} = \frac{1}{3} \cr & \Rightarrow x = 12 \times 3 \cr & \Rightarrow x = 36{\text{ days}} \cr} $$
59
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?
Discuss
Answer & Solution
Answer: Option A
Solution:
6 men will complete the work in 12 days
1 men will complete the work in (6 × 12) = 72 days
8 women will complete two work in 18 days
1 women will complete the work in (8 × 18) = 144 days
18 children will complete the work in 10 days
1 children will complete the work in (18 × 10) = 180 days
$$\eqalign{ & {\text{1 men's 1 day's work}} = \frac{1}{{72}} \cr & {\text{1 women's 1 day's work}} = \frac{1}{{144}} \cr & {\text{1 children's 1 day's work}} = \frac{1}{{180}} \cr} $$
(4 men + 12 women + 20 children)'s 2 day's work
$$\eqalign{ & = 2\left( {\frac{4}{{72}} + \frac{{12}}{{144}} + \frac{{20}}{{180}}} \right) \cr & = 2\left( {\frac{1}{{18}} + \frac{1}{{12}} + \frac{1}{9}} \right) \cr & {\text{L}}{\text{.C}}{\text{.M of 18, 12 and 9}} = {\text{36}} \cr & {\text{ = }}\frac{{2\left( {2 + 3 + 4} \right)}}{{36}} \cr & = \frac{1}{2} \cr & \therefore {\text{Remaining work}} = \frac{1}{2} \cr & \therefore {\text{Required number of men}} \cr & = 72 \times \frac{1}{2} \cr & = 36 \cr} $$
60
16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{Given,}} \cr & {{\text{M}}_1} = 16{\text{ , }}{{\text{M}}_2} = ? \cr & {{\text{D}}_1} = 49{\text{ , }}{{\text{D}}_2} = 24 \cr & {{\text{W}}_1} = 1{\text{ ,}}{{\text{W}}_2} = ? \cr & {\text{According to the question,}} \cr & \frac{{{{\text{M}}_1}{{\text{D}}_1}}}{{{{\text{W}}_1}}}{\text{ = }}\frac{{{{\text{M}}_2}{{\text{D}}_2}}}{{{{\text{W}}_2}}} \cr & \Rightarrow \frac{{16 \times 49}}{1} = \frac{{14 \times 8}}{{{{\text{W}}_2}}} \cr & \Rightarrow {{\text{W}}_2} = \frac{{14 \times 8}}{{16 \times 49}} \cr & \Rightarrow {{\text{W}}_2} = \frac{1}{7} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{1}{7}} \right) \cr & = \frac{6}{7} \cr & {\text{Again,}}\frac{{{{\text{M}}_1}{{\text{D}}_1}}}{{{{\text{W}}_1}}}{\text{ = }}\frac{{{{\text{M}}_2}{{\text{D}}_2}}}{{{{\text{W}}_2}}} \cr & \Rightarrow \frac{{16 \times 49}}{1} = \frac{{{{\text{M}}_2} \times 24}}{{\frac{6}{7}}} \cr & \Rightarrow 16 \times 49 = \frac{{{{\text{M}}_2} \times 24 \times 7}}{6} \cr & \Rightarrow 16 \times 49 = {{\text{M}}_2} \times 4 \times 7 \cr & \Rightarrow {{\text{M}}_2} = \frac{{16 \times 49}}{{4 \times 7}} \cr & \Rightarrow {{\text{M}}_2} = 28 \cr & \therefore {\text{Number of additional men}} \cr & = \left( {28 - 14} \right) \cr & = 14 \cr} $$