"Calculate Re-order level from the following:
"Calculate Re-order level from the following:
Consumption per week: 100-200 units
Delivery period: 14-28 days"
Answer & Solution
Correct Answer:
Option
B
Maximum consumption per week = 200 unit
Maximum delivery time = 28 days = 4 week
Re-order level = 200 x 4 = 800 units.