Direct material cost is $75000 and direct manufacturing labour is $20000, then prime cost would be
Answer & Solution
Correct Answer:
Option
C
Prime cost = Direct material cost + Direct manufacturing labour
= $75000 + $20000 = $95,000
= $75000 + $20000 = $95,000