Flexible budget amount is $57000 and flexible budget variance is $14000, then actual result amount will be
A. $61,000
B. $71,000
C. $43,000
D. $24,000
Answer: Option B
Solution(By Examveda Team)
Actual result = Flexible budget amount + Flexible budget variance= $57000 + $14000 = $71,000
Related Questions on Costing
Basic objective of cost accounting is ________
A. tax compliance.
B. financial audit.
C. cost ascertainment.
D. profit analysis.
Process costing is suitable for ________.
A. hospitals
B. oil refing firms
C. transport firms
D. brick laying firms
The cost which is to be incurred even when a business unit is closed is a _____.
A. imputed cost
B. historical cost
C. sunk cost
D. shutdown cost