For under water concreting.

A. At least 10 percent more cement is required as compared to dry conditions

B. The volume of coarse aggregates shall not be less than one and half times and not more than twice that of fine aggregate

C. De-watering by pumping is not done or until 24 hours thereafter

D. All the above

Answer: Option D