This question belongs to Commerce Costing
Costing
?

If flexible budget amount is $27000 and flexible budget variance is $12000, then actual result amount would be

Answer & Solution
Correct Answer: Option C
Actual result = Flexible budget amount + Flexible budget variance
= $27000 + $12000 = $39,000