ExamVeda
Login
Home
Mine System Engineering
?

In a PERT network, the activities on the critical path are a, b and c. The standard deviations of the durations of these activities are 2, 2 and 1 respectively. The variance of the project duration is

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

No comments yet Be the first to discuss this question.