Examveda
Examveda

In a PERT network, the activities on the critical path are a, b and c. The standard deviations of the durations of these activities are 2, 2 and 1 respectively. The variance of the project duration is

A. 3

B. 5

C. 9

D. 12

Answer: Option C


This Question Belongs to Mining Engineering >> Mine System Engineering

Join The Discussion

Related Questions on Mine System Engineering