Examveda
Examveda

In an opencast mine loading and transporting has been carried out by shovel dumper combination. There is only one shovel is in operation. Dumpers arrive at the rate of 10 dumpers per hour and it takes shovel on an average 5 minutes to load a dumper. Assume arrival is Poisson and service time is exponentially distributed, find the expected number of dumpers waiting to be load in the system.

A. $$\frac{{100}}{{24}}$$

B. $$\frac{{100}}{{12}}$$

C. 2

D. 4

Answer: Option A


This Question Belongs to Mining Engineering >> Mine System Engineering

Join The Discussion

Related Questions on Mine System Engineering