ExamVeda
Login
Home
Mine System Engineering
?

In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression

Answer & Solution
Correct Answer: Option A
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

No comments yet Be the first to discuss this question.