Merricks multiple piece rate system has _______.

Answer & Solution
Correct Answer: Option B
Merricks multiple piece rate system has three rates. According to this plan, three piece rates for a job is fixed. None of these three piece rates are fixed below the normal level. These three rates are applied in the manner given below: Rates Bonus Incentive 1. Upto 83 '/3% Normal Rate 2. Above 83 1/3 % to 100% 110% of Normal Rate 3. Above 110% 120% of Normal Rate