ExamVeda
Login
Home
21
The time study data of an equipment deployed in a mine during a calendar month is given below.
Total working hours = 400
Total maintenance hours = 100
Total hours of actual work = 240
The percentage of utilization of the equipment is
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
22
In an opencast mine loading and transporting has been carried out by shovel dumper combination. There is only one shovel is in operation. Dumpers arrive at the rate of 10 dumpers per hour and it takes shovel on an average 5 minutes to load a dumper. Assume arrival is Poisson and service time is exponentially distributed. Find the expected number of dumpers in the system.
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
23
ISO 9000 Quality Systems DO NOT contain
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
24
The following project network is given with arrows as activities and the numbers by each arrow representing job durations in days. The network has two dummy activities D1 and D2. The minimum completion time of the project in days is
Mine System Engineering mcq question image
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
25
A balanced transportation problem is characterised by
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
26
The feasible region of an LP problem is shown as given below. The maximum value of the objective function Z = 1600X1 + 1200X2 is
Mine System Engineering mcq question image
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
27
In an opencast mine loading and transporting has been carried out by shovel dumper combination. There is only one shovel is in operation. Dumpers arrive at the rate of 10 dumpers per hour and it takes shovel on an average 5 minutes to load a dumper. Assume arrival is Poisson and service time is exponentially distributed. Find the probability that the shovel is sitting idle.
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
28
There are 50 lemon trees in a reclaimed mine area. Each tree produces 800 lemons per year. For each additional tree planted in this area, considering all trees, the output number of fruits per tree drops by 10 lemons in a year. The number of trees that to be added to the existing reclaimed area in order to maximise the total number of lemons in the year is
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
29
In an opencast mine loading and transporting has been carried out by shovel dumper combination. There is only one shovel is in operation. Dumpers arrive at the rate of 10 dumpers per hour and it takes shovel on an average 5 minutes to load a dumper. Assume arrival is Poisson and service time is exponentially distributed. What is expected waiting time of the dumper in the queue?
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
30
A mining project is composed of five activities whose three time estimates in months are given below:
Activity Estimated duration (months)
Optimistic time Most likely time Permissible time
1-2 1 1 7
1-3 2 5 8
2-4 1 1 7
3-4 2 5 14
4-5 3 6 15
The standard deviation of the project length in months is
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board