The time study data of an equipment deployed in a mine during a calendar month is given below.
Total working hours = 400
Total maintenance hours = 100
Total hours of actual work = 240
The percentage of utilization of the equipment is
Total working hours = 400
Total maintenance hours = 100
Total hours of actual work = 240
The percentage of utilization of the equipment is
Answer & Solution
Answer: Option
A
No explanation is given for this question. Let's Discuss on Board