The time study data of an equipment deployed in a mine during a calendar month is given below.
Total working hours = 400
Total maintenance hours = 100
Total hours of actual work = 240
The percentage of utilization of the equipment is
A. 85
B. 80
C. 65
D. 60
Answer: Option A