Examveda
Examveda

The following project network is given with arrows as activities and the numbers by each arrow representing job durations in days. The network has two dummy activities D1 and D2. The minimum completion time of the project in days is
Mine System Engineering mcq question image

A. 13

B. 19

C. 75

D. 68

Answer: Option D


This Question Belongs to Mining Engineering >> Mine System Engineering

Join The Discussion

Related Questions on Mine System Engineering