Number of units are 5000 and per unit price is $60, then flexible budget variable would be
A. $5,000,000
B. $3,000,000
C. $2,000,000
D. $1,000,000
Answer: Option B
Solution (By Examveda Team)
Flexible budget variable = Number of units × per unit price= 5000 × $60 = $3,000,000