Prime cost includes _______.

Answer & Solution
Correct Answer: Option C
Prime cost includes direct materials, direct wages and direct expenses. Prime costs are a firm's expenses directly related to the materials and labor used in production. It refers to a manufactured product's costs, which are calculated to ensure the best profit margin for a company.
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Tejasvi C
Tejasvi C 4 years ago
Answer should be option A,because direct material used is the major portion of product cost while direct labour is the second major element these two are the direct expenditures occurred. While other indirect expenses such as supervisors, clerks salary,electricity,water,gas,stationary etc. Fixed and variable indirect expenses together constitute overheads, these are incidental to production,indirectly.
Thus we can say that prime cost is equal to direct material, direct labour and indirect expenses or overheads.