Sales budget variance is subtracted from flexible budget amount to calculate

Answer & Solution
Correct Answer: Option A
Sales budget variance is subtracted from flexible budget amount to calculate static budget amount. A static budget is a type of budget that incorporates anticipated values about inputs and outputs that are conceived before the period in question begins.