Select the correct statement.

A. Quantity of binder required for tack coat is less than that required for prime coat.

B. Prime coat treatment is given for plugging the voids in water bound macadam during bituminous road construction.

C. Seal coat is the final coat over certain previous bituminous pavements.

D. A bitumen primer is a high viscosity cutback.

Answer: Option D


This Question Belongs to Civil Engineering >> Highway Engineering

Join The Discussion

Comments ( 4 )

  1. भजन कीर्तन
    भजन कीर्तन :
    3 years ago

    D incurrent and all currect

  2. Vivek Parmar
    Vivek Parmar :
    4 years ago

    I think D is incorrect and remaining options are correct

  3. Shakil Ahmed
    Shakil Ahmed :
    4 years ago

    ABc correct

  4. Keerthi S
    Keerthi S :
    5 years ago

    Option B and C also right.
    Give justification for selecting only D

Related Questions on Highway Engineering

The provision of traffic signals at intersections

A. reduces right angled and rear end collisions

B. increases right angled and rear end collisions

C. reduces right angled collisions but may increase rear end collisions

D. reduces rear end collisions but may increase right angled collisions