Select the incorrect statement.

A. Stop or red time of a signal is the sum of go and clearance intervals for the cross flow.

B. Go or green time of a signal is the sum of stop and clearance intervals for the cross flow.

C. Clearance time is generally 3 to 5 seconds.

D. The cycle length is normally 40 to 60 seconds for two phase signals.

Answer: Option B