The labour rate of pay variance can be calculated by which of the following equations?
A. Budgeted labour costs - Actual labour costs
B. (Standard hours - Actual hours) × Actual wage rate
C. (Standard wage rate - Actual wage rate) × Actual hours worked
D. (Standard wage rate - Actual wage rate) × Standard hours worked
Answer: Option C