18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?

A. 9 days

B. 10 days

C. 6 days

D. 8 days

Answer: Option D

Solution(By Examveda Team)

Let the required no of days be x.
18 Men = 36 Boys
1 Man = 2 Boys
∴ 24 Men = 48 Boys
According to the question,
M1D1H1 = M2D2H2
36 × 24 × 6 = (48 + 24) × x × 9
36 × 24 × 6 = 72 × 9 × x
x = $$\frac{{36 \times 6 \times 24}}{{72 \times 9}}$$
x = 8 days

This Question Belongs to Arithmetic Ability >> Time And Work