A and B can do a work in 12 days and 18 days, respectively. They worked for 4 days after which B was replaced by C and the remaining work was completed by A and C in the next 4 days. In how many days will C alone complete 50% of the same work?

A. 24

B. 18

C. 21

D. 36

Answer: Option B


This Question Belongs to Arithmetic Ability >> Time And Work