A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?
A. 60 days
B. 54 days
C. 48 days
D. 50 days
Answer: Option A
Solution(By Examveda Team)
(T.W.) 60 |
|
2 units/day | ↓ |
30 days (A + B) |
(T.W.) 2 0 |
|
1 units/day | ↓ |
20 days (A) |
$$\eqalign{ & = \frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{60}}{1} \cr & = 60{\text{ days}} \cr & \cr & {\bf{Alternate:}} \cr & \left( {{\text{A}} + {\text{B}}} \right) \times {\text{10}} = {\text{A}} \times {\text{20}} \cr & \frac{{{\text{A + B}}}}{{\text{A}}} = \frac{2}{1} \cr & {\text{Total work}} \cr & = 2 \times 30 \cr & = {\text{60 units}} \cr & {\text{Time taken by A alone}} \cr & = \frac{{60}}{1} \cr & = 60{\text{ days}} \cr} $$