A and B working together can do 30% of the work in 6 days. B alone can do the same Work in 25 days. How long will A alone take to complete the same work?
Answer & Solution
Correct Answer:
Option
D

Required answer = $$\frac{{100}}{{5 - 4}}$$ = 100 days