A big advantage of PERT over Gantt charts is that in the former case
A. Activities and events are clearly shown
B. Early start and late finish of an activity are clearly marked
C. Activity times are clear
D. Interrelationship among activities is clearly shown
Answer: Option D
Solution(By Examveda Team)
A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shownRelated Questions on Industrial Engineering and Production Management