A can complete a certain work in 4 minutes, B in 5 minutes, C in 6 minutes, D in 10 minutes and E in 12 minutes. The average number of units of work completed by them per minute will be = ?
A. 0.16
B. 0.40
C. 0.80
D. None of these
Answer: Option A
A. 0.16
B. 0.40
C. 0.80
D. None of these
Answer: Option A
A. 18 days
B. 24 days
C. 30 days
D. 40 days