A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Answer & Solution
Correct Answer:
Option
B
$$\eqalign{
& {\text{18A}} = {\text{12A}} + {\text{8B}} \cr
& {\text{6A}} = {\text{8B}} \cr
& \frac{{\text{A}}}{{\text{B}}} = \frac{4}{3} \cr
& {\text{So, }} \cr
& {\text{Efficiency of A and B are }}4,3. \cr
& {\text{Total work}} \cr
& = 18 \times 4 \cr
& = 72{\text{ units}} \cr
& {\text{So, B will do}} \cr
& = \frac{{72}}{3} \cr
& = 24{\text{ days}} \cr} $$