A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

A. $${\text{ 4}}\frac{4}{5}{\text{ days}}$$

B. $${\text{ 3}}\frac{1}{3}{\text{ days}}$$

C. $${\text{ 5}}\frac{1}{4}{\text{ days}}$$

D. $${\text{2}}\frac{2}{3}{\text{ days}}$$

Answer: Option A

Solution(By Examveda Team)

  A   :   B
Efficiency →   100% : 125%
  4 : 5
Time 5 : 4
  ×1.2↓   ↓×1.2
Actual time   6 days   $${\text{4}}\frac{4}{5}$$ days

This Question Belongs to Arithmetic Ability >> Time And Work