A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

Answer & Solution
Correct Answer: Option A
  A   :   B
Efficiency →   100% : 125%
  4 : 5
Time 5 : 4
  ×1.2↓   ↓×1.2
Actual time   6 days   $${\text{4}}\frac{4}{5}$$ days