A can do a piece of work in 70 days and B is 40% more efficient then A. Then the number of days taken by B to do the same work is = ?
A. 40 dayd
B. 60 days
C. 50 days
D. 45 days
Answer: Option C
Solution(By Examveda Team)
A | : | B | |
Efficiency → | 100% | : | 140% |
5 | : | 7 | |
⤩ | |||
Time | 7 | : | 5 |
×10↓ | ↓×10 | ||
Actual Time | 70 days | 50 days |