A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
A. 110 days
B. 118 days
C. 98 days
D. 120 days
Answer: Option B
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
Join The Discussion